In the Preventive Maintenance application, select the PM record that you want to add an extended date to. On the Frequency tab, ensure that there is a date in the Estimated Next Due Date field. If you need a value in the Estimated Next Due Date field, specify a value. In the Extended Date field, specify a value.
6/17/2018 · Yes, this is correct behaviour in Maximo. If a PM contains an Extended Date on its Frequency tab, the Extended Date overrides the Estimated Next Due Date in a forecast. The first forecasted date is equal to the Extended Date. All subsequent forecasts, however, are based upon the Estimated Next Due Date, not the Extended Date, unless the Adjust Next …
On the Frequency tab, ensure the Estimated Next Due Date field contains a date. In the Extended Date field, specify a value and enter a reason for extending the date. The date must be later than the Estimated Next Due Date. Optional: To adjust this date after the work order for the PM is generated, select the Adjust Next Due Date check box.
This date only applies to the current PM record; it does not apply to other PMs in a PM hierarchy. If the PM has an extension date, MAXIMO ignores the dates in the Active Season fields. MAXIMO always clears the Extended Date and Adjust Next Due Date fields after you generate work orders from this PM.
9/4/2015 · In this case, MAXIMO will ignore the date in the Next Due Date field and will consider the value in Extended Date field as Next Due Date. After MAXIMO creates the WO based on Extended Date, the extended date field will become clear and next due date will be populated based on the frequency. Similarly if the checkbox Use Last Work Order’s Start Date to Calculate Next Due Date is unchecked.
your PM(s) If a PM has an Extended Date , this date overrides the Estimated Next Due Date in a forecast. All subsequent forecasts will use the Estimated Next Due Date . PM Forecasts are not duplicated when a PM is duplicated For PM Hierarchies, only the Top-Level PM is forecasts. Maximo Scheduler uses and can (in certain cases) edit PM, Preventive maintenance forecasting without generating IBM Maximo work orders. Effective PM forecasting allows you to see when your PMs are due to generate and how they will affect your resource availability without having to generate work orders weeks or months in advance in IBM Maximo .
In the Preventive Maintenance application, on the toolbar, click New PM.If the PM field is empty, specify a value.; Enter a description. Click Long Description if you need more space.; In the Location, Asset, or GL Account fields, specify a value. The asset or location is the entity for which you intend to schedule work – you must enter a value in one of these fields.
The estimated next due date on the Time Based Frequency subtab might be January 30, based on average time elapsed between previous oil changes. The estimated next due date on the Meter Based Frequency subtab might be January 15, based on average mileage. The next due date for this PM would be January 15, the earlier of the two dates.